The Nigerian National Petroleum Corporation, NNPC has dismissed the allegation that the Ajaokuta-Kaduna-Kano (AKK) gas pipeline project was inflated to the tune of $1.527 billion.

The Group General Manager, Group Public Affairs of the NNPC, Dr Kennie Obateru in a statement described the accusation as false, baseless and unfounded, stating that the NNPC was considering instituting legal actions against the purveyors of the false news.

It stated that the attention of the Bureau for Public Procurement, BPP had been drawn to the accusation which it completely rejected as the speculative analysis of the online medium, false and not portraying the true position of the BPP’s report on the subject.

He said: “This is clearly a concocted analysis aimed at attacking the character of the Group Managing Director, GMD, of NNPC, Mallam Mele Kolo Kyari, and the integrity of the BPP.

[Also Read] AKK Pipeline Project: OILSERV Ltd Commences Massive Project

Mallam Mele Kyari did not become the GMD until July 2019 and he is being mentioned in a process that took place in 2017 by the account of the publication.

“This is rather unfortunate and malicious, considering that a further cut of $300 million of the contract value was achieved under the Mele Kyari-led NNPC management leading to the recognition by the Federal Executive Council as an unprecedented action.”

Obateru explained that the BPP, following a detailed review and analysis of the procurement bid, confirmed that the unit costs for line pipes adopted by the NNPC for the project were reasonable when compared with current market prices for 40 inches, 36 inches, 20 inches and 14 inches steel pipes, adding that it was on that basis that BPP confirmed and granted certificate of no objection dated August 11, 2017.

He stated that the AKK project underwent a transparent and open competitive tender process that resulted in the emergence of the most competitive bidders, wondering how a competitive tender process could be inflated.

“Approval of all relevant authorities were obtained after an intense scrutiny by the various agencies. This is a deliberate attempt to mislead the Nigerian public with baseless information”, he added.

[Also Read] AKK Pipeline to Boost Nigerian Content Goals

According to the NNPC spokesperson, the AKK pipeline project was one of the key landmark projects that have had transparent processes from inception to date, with the entire evaluation exercise carried out by NNPC and Infrastructure Concession Regulatory Commission, ICRC.

He cited the various stringent due process reviews and scrutiny, internally and externally, which the AKK pipeline project was subjected to, to include: conduct of project bankability study, at project’s conception in 2013, undertaken by Standard Chartered Bank to confirm appetite for attracting financing from international community.

The other scrutiny include: “Execution of project feasibility and Front End Engineering Design, FEED, by a reputable international company, ILF of Germany, in 2014. The details developed at this phase had enough engineering design details to enable a competitive class of estimate to be submitted by the contractors.

“Advertisement of the project in both local and foreign print media in 2013. After completion of the FEED study by ILF in 2015, the prequalified bidders were issued tender documents. Competitive tendering and evaluation of the bids by both NNPC and transaction advisers, Alpine and also by a team from ICRC.

[Also Read] AKK Gas Pipeline Procurement: NNPC Followed Due Process – BPP Clarifies

“Extensive review of the project design and the final cost in 2017 by the BPP, culminating in the issuance of a Certificate of No Objection in August 2017. Receipt of due process certificates for the project, including Original Business Case and Final Business Case from ICRC and Local Content Compliance Certificate from Nigerian Content Development and Management Board, NCDMB, before presenting to the Federal Executive Council, FEC, for approval in December 2017.

“Renegotiation of the contract when financing was not to be provided by the contractors following a stalemate due to the inability of the company awarded the contract to progress financing in 2019, leading to further cut of $300 million of the contract value under the Mele Kyari-led NNPC Management

“Formation of a Steering Committee in July 2020 by Mallam Mele Kyari comprising key project stakeholders as NNPC, Ministry of Finance, Ministry of Justice, the Central Bank, Debt Management Office, Nigeria Extractive Industries Transparency Initiative (NEITI) and representative from the Presidency to ensure transparency in the implementation of the project.”

Obateru explained that after several failed attempts in the last 13 years to commence the AKK project activities, the leadership of Kyari, within one year of stewardship, brought the project on track, leading to the award of the contract at a competitive price and eventual flag off of construction that the world witnessed in June 2020.

[Also Read] ELPS2, OB3, AKK Gas Pipelines Boost Nigeria’s Domestic Footprint – NNPC

He called on all well-meaning Nigerians to give the Mele Kyari-led NNPC management the credit it deserves, even as it encouraged them to follow the execution of the project which was being undertaken in a transparent and aggressive manner in line with Transparency, Accountability, Performance Excellence agenda of the corporation.