Saves $400m with 65,000 bpd increase

Exxon Mobil Corporation has announced that its subsidiary, Esso Exploration and Production Nigeria Limited, has started oil production ahead of schedule at the Erha North Phase 2 project offshore Nigeria.

The Erha North Phase 2 project is a deepwater subsea development located 60 miles offshore Nigeria in 3,300 feet of water and four miles north of the Erha field, which has been producing since 2006.

Also Read: Exxon Mobil not exiting Nigeria – Kachikwu

The Erha North Phase 2 project includes seven wells from three drill centres tied back to the existing Erha North floating production, storage and offloading vessel, reducing additional infrastructure requirements.

The project is estimated to develop an additional 165 million barrels from the currently producing Erha North field. Peak production from the expansion is currently estimated at 65,000 barrels of oil per day and will increase total Erha North field production to approximately 90,000 barrels per day.

Also Read: Exxonmobil Commissions N100m Community Assistance Projects

“Executing successful projects such as Erha North Phase 2 ahead of schedule and under budget results from ExxonMobil’s disciplined project management approach and expertise,”said Neil W. Duffin, president of ExxonMobil Development Company. “We are able to create additional shareholder value by optimising existing infrastructure, which reduces capital spending requirements and improves capital efficiency.”

Duffin said the ahead-of-schedule startup was supported by strong performance from Nigerian contractors, which accounted for more than $2billion of project investment for goods and services,including subsea equipment, facilities and offshore installation.

Also Read: Exxon Mobil not exiting Nigeria – Kachikwu

“These contracts are bringing direct and indirect benefits to the Nigerian economy through project spending and employment, consistent with project objectives,” Duffin said.

ExxonMobil expects to increase its global production volumes this year by 2 percent to 4.1 million oil-equivalent barrels per day, driven by 7 percent liquids growth. The volume increase is supported by the ramp up of projects completed in 2014 and the expected startup of major developments in 2015.

Also Read: ‘Exxon Mobil Key to Developing Ghana’s Oil & Gas Industry’ – President Akufo-Addo

The Erha North field was discovered in 2004 and initial production commenced in 2006. Operator Esso Exploration and Production Nigeria Limited holds a 56.25 percent interest in Erha North Phase 2, while Shell Nigeria Exploration and Production Company holds the remaining 43.75 percent share.