Siemens Energy has confirmed that the company has been selected by the Nigeria Liquefied Natural Gas (NLNG) to provide a cryogenic boil-off gas (BOG) compression train for its Bonny Island liquefaction plant in Finima, Nigeria.
Siemens’ senior vice president for Industrial Applications Products, Arja Talakar, said with more than 20 years of safe and reliable production, the NLNG Bonny Island plant is a staple facility in the global LNG industry, RigZone said in a report yesterday.
He said the order will help NLNG to add BOG handling capability as well as spares for the existing system.
[Also Read] Bonny Light crude programmes finally emerge but Forcados still delayed
According to him, a high-efficiency electric motor will drive the new BOG compression train, which includes two of its centrifugal compressors.
“NLNG’s selection of our cryogenic BOG compression technology is a testament not only to the reliability and performance of our existing equipment at the plant but also to our focused service and ability to meet local content requirements through our in-country presence,” continued Talakar.
“The new BOG compression train will continue to NLNG’s goal of reducing greenhouse gas emissions in a highly sustainable manner.”
[Also Read] Siemens Best Qualified for 25,000MW Grid Expansion – FG
According to Siemens, the compression train will be manufactured, tested and packaged in Duisburg, Germany and will be NLNG’s seventh such facility. It anticipates a free on board delivery of the train in the fourth quarter of 2021.
He explained that owing to current restrictions brought on by the COVID-19 pandemic, all discussions between Siemens Energy and NLNG were conducted remotely via virtual meetings.
“In the end, proactive planning, perseverance and the long-standing relationship between the companies facilitated seamless communication and smooth negotiations virtually,” Talakar said
By Chibisi Ohakah, Abuja