The challenge of gas supply in the nation’s power sector left nearly 2,000 megawatts capacity idle at 12 power plants on Wednesday, The Punch reports.

The nation’s unutilised electricity generation capacity due to gas constraints stood at to 1,987.5MW as of 6am on Wednesday, down from 2,482MW on Tuesday, data obtained from the Federal Ministry of Power, Works and Housing showed. The affected plants are Egbin Thermal Power Station, Geregu I and II, Olorunsogo I and II, Omotosho I, Odukpani, Ihovbor, Alaoji II, Trans-Amadi and Rivers IPPs.

One of the hydro power plants, Shiroro, did not generate any megawatts of electricity on Wednesday as the station was said to be out due to turbine pit flooding. Electricity generation companies have said their inability to pay for gas due to non-payment of a debt of nearly N1tn owed them by the distribution companies will lead to the shutdown of power plants.